Monday, July 19, 2021

Framing has started

Lumber delivery and framing has started

                                The fog rolled in and a heavy mist started the day. Not really typical according to the                                         locals
                            The lumber truck from Spenard Building Supply has the heavy duty telescoping crane.                             He delivered the stick lumber for the basement build out
                                    Then the truck with all the roof trusses showed up





                        It took everyone to get all the trusses off the truck and stacked out of the way



That's Les watching the framers work on the lower level of the house and the gorgeous view.
 
Helping out with some of the easier work
The next day was beautiful, and the crew got a new guy from Paris Texas


The framing crew leader, Ken (on top), is a real perfectionist. Everything has to be level and square. He is a part owner of the contracting company we hired.



Turned the corner, starting to be able to see the window and door locations for the 2 guestrooms





Tilting up another panel that was built on the ground, then put into place and secured




 

July 11th, 2022

 Settling In........ The house was finally painted. Below is the driveway being put in. The grand girls and our daughter Alicia were our fir...